Project Detail
Project Main Menu

Project Overview
Project Name: DOT: Quantico Marine Corps Base Entrance
Project Type:
Project Description: This project will widen Fuller Road which is the entrance road serving the Quantico Marine Corps Base, the Town of Quantico, and communities adjacent to the base. The improvements will involve the widening of the existing four-lane undivided section to a four-lane divided section of roadway with improvements to the intersections of Route 1 and Fuller Heights Road. The design phase is scheduled to start on May 19, 2009 and be completed on January 22, 2010.
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Khattab O. Shammout     
Agency Name: Transportation QPR?: Yes
Magisterial District: Dumfries
Original Budget: ---

Revised Budget:

---
Original Start Date: 5/19/2009

Revised Start Date:

Original End Date: 1/22/2010

Revised End Date:

Last Updated On: 8/17/2009 Maps  Pictures  Documents


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue