Project Detail
Project Main Menu

Project Overview
Project Name: DOT: Route 28 (Linton Hall Road to Fitzwater Drive)
Project Type:
Project Description: This project will widen the current two-lane undivided roadway in the section of Route 28 from Linton Hall Road to Fitzwater Drive to a four-lane divided roadway, which includes the relocation of Vint Hill Road.
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Khattab O. Shammout     
Agency Name: Transportation QPR?: Yes
Magisterial District: Brentsville
Original Budget: $4,000,000.00

Revised Budget:

$4,000,000.00
Original Start Date: 2/1/2009

Revised Start Date:

Original End Date: 6/30/2010

Revised End Date:

Last Updated On: 8/17/2009 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. FY10 RSTP Funds (Estimated)

$2,500,000.00 --- 4/10/2009

2. Transfer RSTP Funds from Balls Ford Road

$1,500,000.00 --- 4/10/2009
       
Total Amount: $4,000,000.00 $4,000,000.00


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue