Project Name: DOT: Dale Boulevard Sidewalk - Hoadly Road to Orangewood Drive
Project Type: TRIP Funds - Sidewalk Construction
Project Description: Provide sidewalk, curb and gutter on the south side of Dale Boulevard (Route 784) from Hoadly Road (Route 642) to Orangewood Drive (Route 2466).
Project Manager: Khattab O. Shammout     send an email
Alternate Manager: Kafayat U. Rahmani     
Agency Name: Transportation QPR?: Yes
Magisterial District: Coles
Original Budget: $100,000.00

Revised Budget:

$100,000.00
Original Start Date: 10/31/2008

Revised Start Date:

Original End Date: 12/31/2010

Revised End Date:

Last Updated On: 8/20/2009 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. FY08 Transfer to project

$50,000.00 --- 5/16/2008

2. FY08 TRIP Funds Allocated

$50,000.00 --- 2/28/2008
       
Total Amount: $100,000.00 $100,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Engineering Design 10/31/2008 2/28/2009 6/30/2009 8/31/2009    
2. VDOT Approval 7/1/2009 9/1/2009 12/31/2009 1/31/2010    
3. Right-of-way and Easements Acquisition 1/1/2010 2/1/2010 3/31/2010    
4. Relocation of Utilities 4/1/2010 6/30/2010    
5. Construction 7/1/2010 12/31/2010    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue