Project Detail
Project Main Menu

Project Overview
Project Name: DOT: Glenkirk Road Improvements
Project Type: TRIP
Project Description: Glenkirk Road improvements to 3R standards north of Vint Hill Road (Route 215) to the south end of the Lake Manassas Dam.
Project Manager: Khattab O. Shammout     send an email
Alternate Manager: Kafayat U. Rahmani     
Agency Name: QPR?: Yes
Magisterial District: Brentsville
Original Budget: $1,525,000.00

Revised Budget:

$1,525,000.00
Original Start Date: 10/1/2007

Revised Start Date:

11/1/2008
Original End Date: 12/31/2009

Revised End Date:

8/31/2010
Last Updated On: 8/20/2009 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. FY 2007 TRIP Funds

$400,000.00 --- 2/6/2007

2. FY 2008 State Secondary Road Funds

$1,125,000.00 ---
       
Total Amount: $1,525,000.00 $1,525,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Engineering Design 10/1/2007 11/1/2008 4/30/2008 1/22/2009    
2. VDOT Approval 5/1/2008 2/1/2009 8/31/2008 7/31/2009    
3. Right-of-way/Easements Acquisition 9/1/2008 8/1/2009 12/31/2008 11/30/2009    
4. Environmental Certification 9/1/2008 8/1/2009 11/30/2008 11/30/2009    
5. Relocation of Utilities 9/1/2008 8/1/2009 12/31/2008 11/30/2009    
6. Bidding Process 11/1/2008 12/1/2009 1/31/2009 2/28/2010    
7. Construction 1/1/2009 3/1/2010 12/31/2009 8/31/2010    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue